Monday 29 September 2014

End panel received

Got our hands on the final end panel and construction plans singing tomorrow and hopefully we can get moving :) 

Friday 26 September 2014

Final documents still not completed

13th day still no documents! They said its a 10-15 day process! This is the third week council can approve your documents before these guys at wisdom can, hopeless! 




Tuesday 16 September 2014

Our block has been pegged!

I was so excited to see our block pegged this morning :) finally some progress! 

Wednesday 10 September 2014

Bank approval

We received our bank commencement letter :) just waiting on wisdom homes now.. 

Tuesday 9 September 2014

Draft end panel signed

We have reviewed our end panel draft, and signed it today. Our cso has ordered our construction plans this is a 10-15 process :( why so long!!! And then our file is put into estimating. Now long now 😀

Friday 5 September 2014

CDC documents sent to bank for final approval

Sent all required documents to bank yesterday, 3-5 day for approval should have out end panel by Monday to sign too, make sure you keep on top I wisdom admin, ensure all documents are signed and sent back on time. We ha e a really great cso, that is very helpful and knowledgable!    

Wednesday 3 September 2014

CDC approved

Our CDC had been approved!! Only took 3 days 😀 now wisdom are preparing end panel draft documents 

Tuesday 2 September 2014

CDC application sent

Finally our CDC application was sent through yesterday, it should come back in 10 days, then next step is out wrap up appointment with wisdom ☺️