Saturday, 29 November 2014
Frames and windows completed
Frames, windows and roof trusses competed last week, now we are waiting for the bricked to finish up the house behind us.. The bricking was supposed to start last week so I hope they are nearly done so ours can start this week :)
Thursday, 13 November 2014
Sunday, 9 November 2014
1st floor frames up
First floor frames went up on Friday the 7 nov, looking so good sorry for the bad photo from my hubby
Tuesday, 28 October 2014
Sunday, 26 October 2014
Waffle pods and pre slab req done
Waffle pods and pre slab requirements are all done Tuesday is slab day :) progress moving well so far can't wait to celebrate!
Thursday, 23 October 2014
Tuesday, 21 October 2014
Piering and slab preparation
Was happy to see that today they have started foundations for our slab..we should expect slab to be done by Tuesday :)