Tuesday, 9 December 2014
Bricks an sand delivered but no bricklaying started
We have been waiting over a month for our bricklayers, we are not happy one bit! With only two weeks till Christmas I hope they get a move on our site supervisor just keeps stringing us along, one more week one more day! So disappointed!
Saturday, 29 November 2014
Frames and windows completed
Frames, windows and roof trusses competed last week, now we are waiting for the bricked to finish up the house behind us.. The bricking was supposed to start last week so I hope they are nearly done so ours can start this week :)
Thursday, 13 November 2014
Sunday, 9 November 2014
1st floor frames up
First floor frames went up on Friday the 7 nov, looking so good sorry for the bad photo from my hubby
Tuesday, 28 October 2014
Sunday, 26 October 2014
Waffle pods and pre slab req done
Waffle pods and pre slab requirements are all done Tuesday is slab day :) progress moving well so far can't wait to celebrate!
Thursday, 23 October 2014
Tuesday, 21 October 2014
Piering and slab preparation
Was happy to see that today they have started foundations for our slab..we should expect slab to be done by Tuesday :)
Thursday, 16 October 2014
Tuesday, 14 October 2014
Production estimation completed
Yesterday we received an email stating that Production estimation have completed our file and we have been moved to construction stage! Unfortunately they haven't excavated as yet they said tomorrow if the rain holds out fingers crossed
Thursday, 9 October 2014
Personalised House number ordered
I know it's rather soon to order our house numbers but at takes a month or so and ordered ours today as I seen a special :)
Sunday, 5 October 2014
Wednesday, 1 October 2014
Production estimating
We received an email stating our file has moved from Customer Service Admin to Production Estimating, woohoo and that we should expect something to happen on site within one week. Gate, loo and excavation first up
Monday, 29 September 2014
End panel received
Got our hands on the final end panel and construction plans singing tomorrow and hopefully we can get moving :)
Friday, 26 September 2014
Final documents still not completed
13th day still no documents! They said its a 10-15 day process! This is the third week council can approve your documents before these guys at wisdom can, hopeless!
Tuesday, 16 September 2014
Wednesday, 10 September 2014
Tuesday, 9 September 2014
Draft end panel signed
We have reviewed our end panel draft, and signed it today. Our cso has ordered our construction plans this is a 10-15 process :( why so long!!! And then our file is put into estimating. Now long now 😀
Friday, 5 September 2014
CDC documents sent to bank for final approval
Sent all required documents to bank yesterday, 3-5 day for approval should have out end panel by Monday to sign too, make sure you keep on top I wisdom admin, ensure all documents are signed and sent back on time. We ha e a really great cso, that is very helpful and knowledgable!
Wednesday, 3 September 2014
CDC approved
Our CDC had been approved!! Only took 3 days 😀 now wisdom are preparing end panel draft documents
Tuesday, 2 September 2014
CDC application sent
Finally our CDC application was sent through yesterday, it should come back in 10 days, then next step is out wrap up appointment with wisdom ☺️
Friday, 8 August 2014
Colours
We have picked everything did it all in one week! Love our colours
Wall tiles in bathroom also included
Thursday, 7 August 2014
Our build in voyager point
We are building a majestic 35 with wisdom homes in voyager point!
Started a new blog because I can not log into our other one.
We started this journey in mid January 2014 when we signed with the sales agent, it's been a lengthy administration process but we are happy so far with wisdom homes.
We are now at our CDC application stage which should take 1-2 weeks.
Then CDC which takes upto 10 working days
Subscribe to:
Posts (Atom)